field research test and verification project was conducted at the recovered energy generation plant at Northern Border Pipeline Company Compressor Station #7 (CS#7) near St. Anthony. Recovered energy generation plant equipment was supplied and installed by ORMAT Technologies, Inc. Basin Electric is purchasing the electricity under a purchase power agreement with an ORMAT subsidiary, which owns and operates the plant.
The different versions of the original document can be found in:
Published on 01/01/2008
Volume 2008, 2008
DOI: 10.2172/931039
Licence: CC BY-NC-SA license
Are you one of the authors of this document?