This report documents the results obtained during the performance of Preoperational Test POTP-007, from December 12, 1997 to March 27, 1998. The main objectives were to demonstrate the operation of the following Cross-Site Transfer System components: Booster pumps P-3125A and P-3125B interlocks and controls, both local and remote; Booster pump P-3125A and P-3125B and associated variable speed drives VSD-1 and VSD-2 performance in both manual and automatic modes; and Water filling, circulation, venting and draining of the transfer headers (supernate and slurry line). As described in reference 1, the following components of the Cross-Site Transfer System that would normally be used during an actual waste transfer, are not used in this specific test: Water Flush System; Valving and instrumentation associated with the 241-SY-A valve pit jumpers; and Valving and instrumentation associated with the 244-A lift station. | This report documents the results obtained during the performance of Preoperational Test POTP-007, from December 12, 1997 to March 27, 1998. The main objectives were to demonstrate the operation of the following Cross-Site Transfer System components: Booster pumps P-3125A and P-3125B interlocks and controls, both local and remote; Booster pump P-3125A and P-3125B and associated variable speed drives VSD-1 and VSD-2 performance in both manual and automatic modes; and Water filling, circulation, venting and draining of the transfer headers (supernate and slurry line). As described in reference 1, the following components of the Cross-Site Transfer System that would normally be used during an actual waste transfer, are not used in this specific test: Water Flush System; Valving and instrumentation associated with the 241-SY-A valve pit jumpers; and Valving and instrumentation associated with the 244-A lift station. | ||
− | |||
− | |||
− | |||
− | |||
− | |||
Line 18: | Line 13: | ||
* [https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf] | * [https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf] | ||
− | * [https://www.osti.gov/servlets/purl/353278 https://www.osti.gov/servlets/purl/353278],[https://core.ac.uk/display/71167838 https://core.ac.uk/display/71167838],[https://academic.microsoft.com/#/detail/1989257015 https://academic.microsoft.com/#/detail/1989257015] | + | * [https://www.osti.gov/servlets/purl/353278 https://www.osti.gov/servlets/purl/353278], |
+ | : [https://core.ac.uk/display/71167838 https://core.ac.uk/display/71167838], | ||
+ | : [https://academic.microsoft.com/#/detail/1989257015 https://academic.microsoft.com/#/detail/1989257015] |
This report documents the results obtained during the performance of Preoperational Test POTP-007, from December 12, 1997 to March 27, 1998. The main objectives were to demonstrate the operation of the following Cross-Site Transfer System components: Booster pumps P-3125A and P-3125B interlocks and controls, both local and remote; Booster pump P-3125A and P-3125B and associated variable speed drives VSD-1 and VSD-2 performance in both manual and automatic modes; and Water filling, circulation, venting and draining of the transfer headers (supernate and slurry line). As described in reference 1, the following components of the Cross-Site Transfer System that would normally be used during an actual waste transfer, are not used in this specific test: Water Flush System; Valving and instrumentation associated with the 241-SY-A valve pit jumpers; and Valving and instrumentation associated with the 244-A lift station.
The different versions of the original document can be found in:
Published on 01/01/1998
Volume 1998, 1998
DOI: 10.2172/353278
Licence: CC BY-NC-SA license
Are you one of the authors of this document?