(Created page with " == Abstract == This report documents the results obtained during the performance of Preoperational Test POTP-007, from December 12, 1997 to March 27, 1998. The main objectiv...")
 
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
  
 
This report documents the results obtained during the performance of Preoperational Test POTP-007, from December 12, 1997 to March 27, 1998. The main objectives were to demonstrate the operation of the following Cross-Site Transfer System components: Booster pumps P-3125A and P-3125B interlocks and controls, both local and remote; Booster pump P-3125A and P-3125B and associated variable speed drives VSD-1 and VSD-2 performance in both manual and automatic modes; and Water filling, circulation, venting and draining of the transfer headers (supernate and slurry line). As described in reference 1, the following components of the Cross-Site Transfer System that would normally be used during an actual waste transfer, are not used in this specific test: Water Flush System; Valving and instrumentation associated with the 241-SY-A valve pit jumpers; and Valving and instrumentation associated with the 244-A lift station.
 
This report documents the results obtained during the performance of Preoperational Test POTP-007, from December 12, 1997 to March 27, 1998. The main objectives were to demonstrate the operation of the following Cross-Site Transfer System components: Booster pumps P-3125A and P-3125B interlocks and controls, both local and remote; Booster pump P-3125A and P-3125B and associated variable speed drives VSD-1 and VSD-2 performance in both manual and automatic modes; and Water filling, circulation, venting and draining of the transfer headers (supernate and slurry line). As described in reference 1, the following components of the Cross-Site Transfer System that would normally be used during an actual waste transfer, are not used in this specific test: Water Flush System; Valving and instrumentation associated with the 241-SY-A valve pit jumpers; and Valving and instrumentation associated with the 244-A lift station.
 
Document type: Report
 
 
== Full document ==
 
<pdf>Media:Draft_Content_391458604-beopen366-9919-document.pdf</pdf>
 
  
  
Line 18: Line 13:
 
* [https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf]
 
* [https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf https://digital.library.unt.edu/ark:/67531/metadc674721/m2/1/high_res_d/353278.pdf]
  
* [https://www.osti.gov/servlets/purl/353278 https://www.osti.gov/servlets/purl/353278],[https://core.ac.uk/display/71167838 https://core.ac.uk/display/71167838],[https://academic.microsoft.com/#/detail/1989257015 https://academic.microsoft.com/#/detail/1989257015]
+
* [https://www.osti.gov/servlets/purl/353278 https://www.osti.gov/servlets/purl/353278],
 +
: [https://core.ac.uk/display/71167838 https://core.ac.uk/display/71167838],
 +
: [https://academic.microsoft.com/#/detail/1989257015 https://academic.microsoft.com/#/detail/1989257015]

Latest revision as of 11:57, 22 January 2021

Abstract

This report documents the results obtained during the performance of Preoperational Test POTP-007, from December 12, 1997 to March 27, 1998. The main objectives were to demonstrate the operation of the following Cross-Site Transfer System components: Booster pumps P-3125A and P-3125B interlocks and controls, both local and remote; Booster pump P-3125A and P-3125B and associated variable speed drives VSD-1 and VSD-2 performance in both manual and automatic modes; and Water filling, circulation, venting and draining of the transfer headers (supernate and slurry line). As described in reference 1, the following components of the Cross-Site Transfer System that would normally be used during an actual waste transfer, are not used in this specific test: Water Flush System; Valving and instrumentation associated with the 241-SY-A valve pit jumpers; and Valving and instrumentation associated with the 244-A lift station.


Original document

The different versions of the original document can be found in:

https://core.ac.uk/display/71167838,
https://academic.microsoft.com/#/detail/1989257015
Back to Top

Document information

Published on 01/01/1998

Volume 1998, 1998
DOI: 10.2172/353278